JCT master programme and delay notice checklist

A checklist for reviewing the Contractor's master programme and notices of delay under the JCT Design and Build and Standard Building Contracts 2016.

Download the Excel templateFree, no account needed.

How to use it

  1. Use the first section each time a revised master programme is received.
  2. Use the second section for each notice of delay: record what the notice contains and what is missing.
  3. Note the date the required particulars were received: the timescale for fixing a new Completion Date runs from then.
  4. Clause numbers are shown for Design and Build (DB) and Standard Building Contract (SBC); check your edition.

Master programme

ClauseRequirementWhat to look for
DB 2.9 / SBC 2.9.1.2Master programme provided for the execution of the WorksA logic-linked programme with a completion milestone.
Contract ParticularsCompletion Date and any Section Completion Dates shownPlanned dates compared with the contract dates; any later date explained.
Good practiceProgress shown against a data dateNo incomplete work left before the data date.
Good practiceLogic complete enough to show the effect of delaysFew open ends; no loops.
DB 2.9 / SBC 2.9.1.2Programme amended after a decision fixing a later Completion DateThe new Completion Date and its effect are shown.

Notice of delay

ClauseRequirementWhat to look for
DB 2.24 / SBC 2.27Written notice given when it became reasonably apparent that progress is or is likely to be delayedDate of the notice compared with the date the delay became apparent.
DB 2.24 / SBC 2.27The material circumstances, including the cause of the delayA clear description of what happened and when.
DB 2.24 / SBC 2.27Each event identified as a Relevant EventThe Relevant Event relied on is named.
DB 2.24 / SBC 2.27Particulars of the expected effectsAffected activities identified on the programme, with the logic to completion.
DB 2.24 / SBC 2.27Estimate of the expected delay in completionA number of days, for the Works and any Section.
DB 2.24 / SBC 2.27Further notices and updated particulars as the delay developsUpdates received when the estimate changes.
DB 2.25 / SBC 2.28Decision on a new Completion Date within the period stated after receipt of the required particularsDiary the decision date from receipt of the particulars.

JCT Design and Build Contract 2016 and JCT Standard Building Contract 2016. Clause references are to the unamended edition named above. Contracts are often amended: check every reference against your own contract. This template is a starting point for your review, not legal advice.