NEC4 programme acceptance checklist

A clause-by-clause checklist for reviewing a programme submitted for acceptance under the NEC4 Engineering and Construction Contract, ready for the two-week response.

Download the Excel templateFree, no account needed.

How to use it

  1. Enter the programme reference and the date it was received: the Project Manager has two weeks to respond (clause 31.3).
  2. Work through each line and record whether the programme shows it, with a short comment.
  3. Anything marked 'No' becomes a reason for not accepting. Group them under the four reasons in clause 31.3.
  4. Keep the completed checklist with the programme submission as your record of the review.

Clause 31.2: what each programme must show

ClauseRequirementWhat to look for
31.2The starting date, access dates, Key Dates and Completion DateDates match the Contract Data; any later date is explained.
31.2Planned CompletionA clear completion milestone; if later than the Completion Date, the reason is stated.
31.2The order and timing of the operations the Contractor plans to doLogic-linked activities; few open ends; no loops; sensible lags.
31.2The order and timing of the work of the Client and OthersClient works, utilities, statutory bodies and other contractors are shown as agreed or as in the Scope.
31.2The dates when the Contractor plans to meet each Condition for the Key DatesEach Key Date condition has its own milestone.
31.2Provisions for float and time risk allowancesFloat is visible; time risk allowances are identified, not hidden in durations.
31.2Provisions for health and safety requirements and contract proceduresDurations allow for safety requirements and for the response periods in the contract.
31.2Dates when the Contractor needs access, acceptances, Plant and Materials and other things from the Client, and information from OthersInformation-required and access-required dates are shown and are realistic.
31.2For each operation, how the Contractor plans to do the work, with principal Equipment and resourcesA method statement or narrative is included with the submission.
31.2Other information which the Scope requiresCheck the Scope for format, level of detail and any specific requirements.

Clause 32.1: what each revised programme must also show

ClauseRequirementWhat to look for
32.1Actual progress achieved on each operation and its effect on the remaining workA data date; progress recorded; no incomplete work left in the past.
32.1The effects of implemented compensation eventsEach implemented event is reflected and traceable.
32.1How the Contractor plans to deal with any delays and to correct notified DefectsSlippage since the last accepted programme is explained, with recovery measures.
32.1Any other changes the Contractor proposes to make to the Accepted ProgrammeChanges in sequence, method or durations are identified.

Clauses 32.2 and 31.3: timing and response

ClauseRequirementWhat to look for
32.2Revised programme submitted within the interval stated in the Contract DataCompare the data dates of successive programmes.
31.3Response within two weeks of submissionAcceptance, or the reasons for not accepting.
31.3Reasons limited to those in the contractNot practicable; does not show the required information; does not represent the plans realistically; does not comply with the Scope.

NEC4 Engineering and Construction Contract (June 2017, with amendments). Clause references are to the unamended edition named above. Contracts are often amended: check every reference against your own contract. This template is a starting point for your review, not legal advice.