How to use it
- Copy the activities planned in the next three weeks from the programme, with their activity IDs.
- Mark the days each activity is planned in the week columns.
- For each activity, record whether its constraints are cleared: information, materials, labour, access, permits and predecessor work.
- Review it at the weekly coordination meeting and carry forward anything not ready.
Columns
Activity ID, Activity, Package / contractor, Planned start, Planned finish, Information, Materials, Labour, Access, Permits, Predecessor complete, Ready to start, Notes, plus a column for each working day of the three weeks.